DirtyWaterWatch Public waters. Public record.

Connecticut / Reports /

Treatment plant bypass reported — NEW MILFORD, Jul 1, 2026

Ended (as reported) · NEW MILFORD (CT DEEP Performance Dashboard)

Source: NEW MILFORD (CT DEEP Performance Dashboard) via CT DEEP CSO/SSO Performance Dashboard (QScend), record 10856, the source gives no report time, retrieved 2026-11-02 11:20 UTC · Read the original notice

Current status from this report

This report does not set a map status as of Nov 2, 2026, 11:21 AM EST. Check its dates and the status rules.

A report is not a test of the water. See how we assign statuses.

Read the original notice · Report an error

1. Reported wastewater outlet

Operator named in the record: NEW MILFORD. Outlet: “Treatment Plant, 123 West St, New Milford, CT”. Location: not given in the report or in the outlet records.

Outfall: a pipe or outlet where wastewater enters a water body.

2. Waters named in the notice

The notice names no water. Not linked to a mapped water.

3. Estimated downstream stretch

We estimate routes only on rivers before they become tidal. We do not estimate routes through tidal water or lakes.

When it happened and when it was reported

Event and notice times use Eastern Time (EST or EDT). Retrieval times use Coordinated Universal Time (UTC).

Started
Ended
Detail provided by the source
Times known to the minute
Reported to the source
not given
Published
not given
Source last updated
not given
Last retrieved by DirtyWaterWatch

What and how much

Type
Treatment bypass: wastewater skips one or more treatment steps.
Status in the record
Ended (as reported)
Material
“Raw Sewage”
Volume
“< 100 gals by visual assessment of affected areas.” (estimated)
Volume as reported
“< 100 gals by visual assessment of affected areas.”

Advice from NEW MILFORD (CT DEEP Performance Dashboard)

This report includes no advice. Check current local health notices.

Advice period
This report does not state a period. See the rule DirtyWaterWatch applies and its source.
Basis
not stated

Source and versions

Source
CT DEEP CSO/SSO Performance Dashboard (QScend)
Source record number
10856
Original notice
Read the original notice
Earlier version
None: this is the first record
Later versions
None

Record details

Record details
Record identifierct-deep:10856
Source identifierct-deep
Source record number10856
Earlier versionNot provided
TypeTreatment plant bypass
Status in the reportEnded (as reported)
Sewer operator identifierct-new-milford
Sewer operatorNEW MILFORD
Federal wastewater discharge permit (NPDES)Not provided
Outlet numberNot provided
Outlet nameTreatment Plant, 123 West St, New Milford, CT
Water named in the reportNot provided
Linked watersNot provided
How this report was linked to the waternot linked to a mapped water
LatitudeNot provided
LongitudeNot provided
Location sourceNot provided
Location accuracy, in metresNot provided
StartedJul 1, 2026, 5:00 AM EDT (2026-07-01T05:00:00-04:00)
EndedJul 1, 2026, 5:30 AM EDT (2026-07-01T05:30:00-04:00)
Detail provided by the sourceto the minute
Reported to the sourceNot provided
PublishedNot provided
Source last updatedNot provided
Last retrieved by DirtyWaterWatchNov 2, 2026, 6:20 AM EST (2026-11-02T11:20:59Z)
MaterialRaw Sewage
Volume, in gallonsNot provided
Volume as reported< 100 gals by visual assessment of affected areas.
How volume was determinedestimated
AuthorityNEW MILFORD (CT DEEP Performance Dashboard)
AdviceNot provided
Advice period, in hoursNot provided
Basis of the advice periodNot provided
Original noticehttps://deepct.qscend.mygovcenter.com/cms/cms?id=1

Original source data

{
  "Reporting Utility": "NEW MILFORD",
  "Status": "Closed",
  "Incident Type": "Sewage Bypass",
  "Weather Conditions": "Rain less than 1\" per hour",
  "Date Bypass Began or was Discovered": "07/01/2026",
  "Event Start Time": "05:00 AM",
  "Location of Bypass": "Treatment Plant",
  "Type of Bypass": "Raw Sewage",
  "Cause of Bypass": "Other",
  "Cause of Bypass Other Explanation": "Mechanical Bar Screen in headworks building was partially plugged with debris from a storm surge due to heavy rains during thunder storms.",
  "How was Incident Discovered": "Incident was discovered when operators arrived at Treatment Plant and started daily inspections and workday. The incident was discovered at 7:45 am but we believe the incident started at 5:00 am and ended at 5:30 am from flow data Obtained from SCADA. upo",
  "Estimated Quantity or Rate of Discharge": "< 100 gals by visual assessment of affected areas.",
  "How was estimated Quantity or Rate Determined": "A visual assessment of affected areas and took videos of all areas around headworks while doing a workaround to make sure there was no evidence of sewage debris: rags, sanitary items, toilet paper, grease balls etc. in the wooded areas near Headworks. Mos",
  "Reach Waterbody": "No",
  "Request ID": "10856",
  "Waterbody Name": null,
  "Date Bypass Ended": "07/01/2026",
  "Event End Time": "05:30 AM",
  "Final Quantity": "< 100 gals by visual assessment of affected areas.",
  "How was Final Volume Determined": null,
  "How incident was resolved": "The deluge of of flow subsided when thunder storms ended and bar screen was cleaned.",
  "Municipality": "New Milford",
  "Address": "123 West St, New Milford, CT",
  "_view": "SSO DATA VIEW"
}

Source: NEW MILFORD (CT DEEP Performance Dashboard) via CT DEEP CSO/SSO Performance Dashboard (QScend), record 10856, the source gives no report time, retrieved 2026-11-02 11:20 UTC · Read the original notice